News Flash

Posted on: October 23, 2020

Project Update 10/23/2020

SR 91 Turn Lane Project Update

Over the past two weeks the contractor has completed installation of 16 inch water line at the north end of the project. Over the next two weeks the contractor will be testing and chlorinating the 16 inch water line and starting installation of 8 inch wat...

Read on...

SR 91 North Turn Lane Improvement Project
Posted on: October 9, 2020

Project Update 10/9/2020

SR 91 Turn Lane Project Update

Over the past two weeks the contractor has continued to work on the installation of 16 inch water line at the north end of the project, including installation of fire hydrants. The testing and chlorination of the 8” water line at the south end o...

Read on...

SR 91 North Turn Lane Improvement Project
Posted on: September 25, 2020

Project Update 9/25/2020

SR 91 Turn Lane Project Update

Over the past two weeks the contractor has completed the installation of 8 inch water line at the south end of the project, installed bore pits for upcoming 16 inch water main work, completed minor grading, and started saw cutting the pavement. Over the n...

Read on...

SR 91 North Turn Lane Improvement Project
Posted on: September 15, 2020

Project Update 9/15/20

sr 91

Over the past two weeks, the contractor has completed clearing and installing erosion and sediment controls along SR 91. Dominion East Ohio Gas has also finished the gas pipe relocation work. During the next two weeks. the contractor will begin water line...

Read on...

SR 91 North Turn Lane Improvement Project
Posted on: September 2, 2020

SR 91 Turn Lane Project Underway

SR 91 Turn Lane Project Update

The SR 91 North Turn Lane Project construction is underway. The project is designed to improve safety, reduce traffic congestion, and provide better pedestrian and bicycle travel between Brandywine Drive and Middleton Road.

Improvements include left-turn l...

Read on...

SR 91 North Turn Lane Improvement Project
Posted on: August 31, 2020

Project Update 6/4/2020

SR 91 Turn Lane Project Update

Starting tomorrow, June 5, Dominion East Ohio Gas (EOG) Company will have their contractor beginning the gas main and service relocation work for the SR 91 N. Turn Lane project.  The gas pipe relocation work is planned at various locations along ...

Read on...

SR 91 North Turn Lane Improvement Project
Posted on: August 31, 2020

Project Update 3/9/2020

SR 91 Turn Lane Project Update

Tree cutting has been completed along the project corridor and removal of logs will take place later this week. During the log removal work, two way traffic will be maintained.

SR 91 North Turn Lane Improvement Project
Posted on: August 31, 2020

Project Update 3/2/2020

SR 91 Turn Lane Project Update

Tree clearing has commenced on the project and is anticipated to last approximately two weeks, weather permitting. The tree removal is taking place ahead of the roadway work in order to meet the project’s environmental requirements. During the t...

Read on...

SR 91 North Turn Lane Improvement Project
Posted on: August 31, 2020

Project Update 1/23/2020

SR 91 Turn Lane Project Update

Right-of-way acquisition is anticipated to be completed by late January, 2020.  The next step for the project is for utility companies to begin moving infrastructure (pipes, poles, etc.) that may be in conflict with the roadway improvements. In a...

Read on...

SR 91 North Turn Lane Improvement Project
Posted on: August 31, 2020

Project Update 4/19/2019

SR 91 Turn Lane Project Update

Right-of-way acquisition is on-going and anticipated to be completed later this year.  After the right-of-way acquisition process is complete, affected utility infrastructure such as telephone poles, underground gas lines, etc. will be moved in p...

Read on...

SR 91 North Turn Lane Improvement Project