News Flash

Posted on: February 16, 2021

Project Update 2/12/2021

SR 91 Turn Lane Project Update

Over the past two weeks the contractor has continued to install storm sewers and headwalls.   Over the next two weeks the contractor will continue installing additional storm sewers and may start electrical conduit installation.

Read on...

SR 91 North Turn Lane Improvement Project
Posted on: January 29, 2021

Project Update 1/29/2021

SR 91 Turn Lane Project Update

Over the past two weeks the contractor has continued to install storm sewers and headwalls and completed concrete trench repairs at Herrick Park Drive and Hines Hill Road.   Also, Hudson Public Power installed temporary street lights at the inter...

Read on...

SR 91 North Turn Lane Improvement Project
Posted on: January 15, 2021

Project Update 1/15/2021

SR 91 Turn Lane Project Update

Over the past two weeks the contractor has installed drainage/ storm sewer work near Herrick Park Drive and poured concrete for culvert headwalls.  Over the next two weeks the contractor will be working on additional storm sewer installation, hea...

Read on...

SR 91 North Turn Lane Improvement Project
Posted on: December 21, 2020

Project Update 12/21/2020

SR 91 Turn Lane Project Update

Over the past two weeks the contractor has installed drainage/ storm sewer work along entire project corridor.  Most of the east side storm sewer has been completed.  Over the next couple days the contractor will be continuing with drain...

Read on...

SR 91 North Turn Lane Improvement Project
Posted on: December 4, 2020

Project Update 12/4/2020

SR 91 Turn Lane Project Update

Over the past two weeks the contractor has installed drainage/ storm sewer work along entire project corridor and installed 2 waterline services.  All waterline items have now been completed.  Over the next two weeks the contractor will ...

Read on...

SR 91 North Turn Lane Improvement Project
Posted on: November 23, 2020

Project Update 11/20/2020

SR 91 Turn Lane Project Update

Over the past two weeks the contractor has installed drainage/storm sewer work along entire project corridor.  Waterline items have been completed except for two service connections.  Over the next two weeks the contractor will be instal...

Read on...

SR 91 North Turn Lane Improvement Project
Posted on: November 5, 2020

Project Update 11/5/2020

SR 91 Turn Lane Project Update

Over the past two weeks the contractor has completed installation of 8 inch Akron water line near Hines Hill Road and Edge View Drive.  Over the next two weeks the contractor will be testing and chlorinating the 16 inch water line, completing wat...

Read on...

SR 91 North Turn Lane Improvement Project
Posted on: October 23, 2020

Project Update 10/23/2020

SR 91 Turn Lane Project Update

Over the past two weeks the contractor has completed installation of 16 inch water line at the north end of the project. Over the next two weeks the contractor will be testing and chlorinating the 16 inch water line and starting installation of 8 inch wat...

Read on...

SR 91 North Turn Lane Improvement Project
Posted on: October 9, 2020

Project Update 10/9/2020

SR 91 Turn Lane Project Update

Over the past two weeks the contractor has continued to work on the installation of 16 inch water line at the north end of the project, including installation of fire hydrants. The testing and chlorination of the 8” water line at the south end o...

Read on...

SR 91 North Turn Lane Improvement Project
Posted on: September 25, 2020

Project Update 9/25/2020

SR 91 Turn Lane Project Update

Over the past two weeks the contractor has completed the installation of 8 inch water line at the south end of the project, installed bore pits for upcoming 16 inch water main work, completed minor grading, and started saw cutting the pavement. Over the n...

Read on...

SR 91 North Turn Lane Improvement Project
Posted on: September 15, 2020

Project Update 9/15/20

sr 91

Over the past two weeks, the contractor has completed clearing and installing erosion and sediment controls along SR 91. Dominion East Ohio Gas has also finished the gas pipe relocation work. During the next two weeks. the contractor will begin water line...

Read on...

SR 91 North Turn Lane Improvement Project
Posted on: August 31, 2020

Project Update 6/4/2020

SR 91 Turn Lane Project Update

Starting tomorrow, June 5, Dominion East Ohio Gas (EOG) Company will have their contractor beginning the gas main and service relocation work for the SR 91 N. Turn Lane project.  The gas pipe relocation work is planned at various locations along ...

Read on...

SR 91 North Turn Lane Improvement Project
Posted on: August 31, 2020

Project Update 3/9/2020

SR 91 Turn Lane Project Update

Tree cutting has been completed along the project corridor and removal of logs will take place later this week. During the log removal work, two way traffic will be maintained.

SR 91 North Turn Lane Improvement Project
Posted on: August 31, 2020

Project Update 3/2/2020

SR 91 Turn Lane Project Update

Tree clearing has commenced on the project and is anticipated to last approximately two weeks, weather permitting. The tree removal is taking place ahead of the roadway work in order to meet the project’s environmental requirements. During the t...

Read on...

SR 91 North Turn Lane Improvement Project
Posted on: August 31, 2020

Project Update 1/23/2020

SR 91 Turn Lane Project Update

Right-of-way acquisition is anticipated to be completed by late January, 2020.  The next step for the project is for utility companies to begin moving infrastructure (pipes, poles, etc.) that may be in conflict with the roadway improvements. In a...

Read on...

SR 91 North Turn Lane Improvement Project
Posted on: August 31, 2020

Project Update 4/19/2019

SR 91 Turn Lane Project Update

Right-of-way acquisition is on-going and anticipated to be completed later this year.  After the right-of-way acquisition process is complete, affected utility infrastructure such as telephone poles, underground gas lines, etc. will be moved in p...

Read on...

SR 91 North Turn Lane Improvement Project