Over the past two weeks the contractor has completed all driveways along the west side of the project and started final grading, seeding, and mulching in all areas of the project. Over the next two weeks the contractor will be completing the final surface course of asphalt across the entire project and completing all final restoration of the project. Asphalt surface paving will start on Monday, September 20, and likely continue for approximately 3 days. Expect longer than usual delays during this time due to the longer construction zones needed for this type of paving operation. The tentative plan for surface paving is:
- Monday - Pave the east (northbound) lane
- Tuesday - Pave the west (southbound) lane
- Wednesday – Pave intersections