Road Construction Updates

Posted on: September 10, 2021

Resurfacing of Hudson Aurora Road Begins Saturday

Hudson aurora resurfacing

Resurfacing of Hudson Aurora Road, between Stow Road and Herrick Park Drive, will begin on Saturday, September 11. See the anticipated schedule below. Work during the week will be performed outside of school peak hours to avoid major congestion. Thank you for your patience during this work.

  • Saturday, September 11 - Mill surface.
  • Monday, September 13 - Proof roll to identify any poor road base areas.
  • Tuesday, September 14 - Repair any identified poor road base areas.
  • Wednesday, September 15 - Install chip-seal. This prevents future reflective cracking through final pavement layer.
  • Thursday, September 16 - Place leveling course of asphalt.
  • Friday, September 17 - Adjust any metal manhole, valve, and inlet lids.
  • Saturday, September 18 - Place final surface course of asphalt.