SR 91 North Turn Lane Improvement Project

Posted on: August 16, 2021

Project Update 8/16/21

SR 91 Turn Lane Project Update

Over the past two weeks the contractor has completed base and intermediate paving along the east side of the project, installed electrical connections, installed a concrete apron, and installed some signs. Over the next two weeks the contractor will be working the along the west side of the project preparing  pavement sub base for paving, starting driveway apron replacements, and some landscaping.

Facebook Twitter Email

Other News in SR 91 North Turn Lane Improvement Project

SR 91 Turn Lane Project Update

Project Update 9/20/2021

Posted on: September 20, 2021
SR 91 Turn Lane Project Update

Project Update 08/30/2020

Posted on: August 30, 2021
SR 91 Turn Lane Project Update

Project Update 1/29/2021

Posted on: January 29, 2021
SR 91 Turn Lane Project Update

Project Update 1/15/2021

Posted on: January 15, 2021
SR 91 Turn Lane Project Update

Project Update 12/21/2020

Posted on: December 21, 2020
SR 91 Turn Lane Project Update

Project Update 12/4/2020

Posted on: December 4, 2020
SR 91 Turn Lane Project Update

Project Update 11/20/2020

Posted on: November 23, 2020
SR 91 Turn Lane Project Update

Project Update 11/5/2020

Posted on: November 5, 2020
SR 91 Turn Lane Project Update

Project Update 10/23/2020

Posted on: October 23, 2020
SR 91 Turn Lane Project Update

Project Update 10/9/2020

Posted on: October 9, 2020
SR 91 Turn Lane Project Update

Project Update 9/25/2020

Posted on: September 25, 2020
SR 91 Turn Lane Project Update

Project Update 6/4/2020

Posted on: August 31, 2020
SR 91 Turn Lane Project Update

Project Update 3/9/2020

Posted on: August 31, 2020
SR 91 Turn Lane Project Update

Project Update 3/2/2020

Posted on: August 31, 2020
SR 91 Turn Lane Project Update

Project Update 1/23/2020

Posted on: August 31, 2020
SR 91 Turn Lane Project Update

Project Update 4/19/2019

Posted on: August 31, 2020