Over the past two weeks, the contractor has completed clearing and installing erosion and sediment controls along SR 91. Dominion East Ohio Gas has also finished the gas pipe relocation work. During the next two weeks. the contractor will begin water line work at the south end of the project.
Traffic will be maintained, but delays may occur at times throughout the project.