Starting tomorrow, June 5, Dominion East Ohio Gas (EOG) Company will have their contractor beginning the gas main and service relocation work for the SR 91 N. Turn Lane project. The gas pipe relocation work is planned at various locations along the project corridor between Brandywine Drive and Middleton Road. The gas main and service relocation work is necessary as the upcoming roadway project includes roadway widening, storm sewer and water main improvements that will be in conflict with Dominion’s existing gas pipe network.
The gas line relocation work is scheduled to be completed by August, 2020 and affected residents have been notified directly by Dominion EOG via letter of the upcoming work.
During the course of the work, the contractor will maintain two-way traffic along SR 91 and at side streets. Traffic delays can be expected when the contractor must work in/near the pavement. City staff will be inspecting the work during its duration. Should you have any questions, please contact Brad Kosco or Tony Calabro at the City of Hudson Engineering Department. .