Akron Water provided an update on its Middleton Road Waterline Replacement Project this week.
The project includes two parts:
- The replacement of the existing water main along Middleton Road
- Bolt replacements at joints on the Akron water main on State Route 91 north of Middleton Road to the north Hudson/Twinsburg corporation line
The project is scheduled to begin in March 2019 once the winter weather has cleared. The work is scheduled to last approximately 200 days. The road surface will be maintained during the course of the water project.
Resurfacing of Middleton Road will take place as soon as the water line work is completed and accepted. If the resurfacing of Middleton Road needs pushed to 2020, the City of Hudson's Public Works Department will maintain Middleton Road in 2019.