Construction on the North Main Street Improvement Project was originally scheduled to begin April 15, but due to the mild weather, we've asked the contractor to complete the remaining storm sewer work on this project beginning on Aurora Street on Monday, March 13. The work will be primarily on the east side of North Main Street, between Aurora Street and Owen Brown Street.
Nightly lane closures will be necessary to complete the storm sewer work in the scheduled two- to three-week period, weather permitting. Work may also be performed during the day, including work on the sidewalk and lighting and traffic control. Traffic and access to driveways will be maintained. Expect delays.
If you have questions about this project, please call the Engineering Department at (330) 342-1770. Project information is also available here. Thank you for your patience during this improvement project.