Merchants have asked us to begin construction on the North Main Street Improvement Project as soon as possible. With work originally scheduled to begin April 15, due to the mild weather, we've asked Mr. Excavator to complete the remaining storm sewer work on this project beginning on Aurora Street on Monday, March 13.
Staging starts Monday, and the actual construction work will begin Tuesday, March 14 at 8 p.m., primarily on the east side of North Main Street, between Aurora Street and Owen Brown Street.
Nightly lane closures will be necessary to complete the storm sewer work in the scheduled two- to three-week period, weather permitting. Work may also be performed during the day, including work on the sidewalk and lighting and traffic control. Traffic and access to driveways will be maintained.
If you have questions about this project, please call the Engineering Department at (330) 342-1770 or via email. Project information is also available here. Want to receive updates on this project? Sign up here. Thank you for your patience during this improvement project.