As part of the Connectivity Plan and the proposed Village of Boston Heights to Hudson Trail, the City of Hudson and the Ohio Department of Natural Resources considered construction of a portion of the Heights to Hudson Trail which would consist of a 10-foot wide asphalt path.The trail was originally planned for construction in 2017-2018. 

Trail alignment:

  • Hines Hill Rd. and W. Prospect St. intersection, to:
  • W. Prospect St. and Hunting Hollow Dr., to, 
  • Hunting Hollow Dr. and Valley View Rd. intersection,
  • Ending at the intersection of Valley View and Darrow Rd. 


Contact Information:


Jonathon Szalay, Engineering Project Designer
Phone: (330) 342-1770
Email

Current Status

In August, 2017, the City sent letters to resident along Hunting Hollow Drive asking for input on the alignment of a new trail alignment given three options:

  • Option 1 is a 10-ft wide sidewalk along Hunting Hollow Drive. The path would be located on the south side of the road, within the City’s right-of-way.
  • Option 2 is a 12-ft wide asphalt path. This option would be located in the Ohio Edison easement behind the homes along the turnpike.
  • Option 3 is to add “Share the Road” signs in both directions along Hunting Hollow Drive. “No Parking” signage along the north side of the road will be considered.

The results of the resident survey concluded that the owners along Hunting Hollow would prefer Option 3 - to have the proposed trail alignment run down the existing asphalt road with pavement markings and signs.

Using public input, the project design along Valley View Road and Hunting Hollow Drive is on-going. 

Due for the need of additional design required for the off-road trail along Valley View Road to cross over a Summit County Bridge, the project is postponed. City staff is currently in the process of analyzing the best design to use to meet both Summit County and City requirements. The City will continue design throughout the fall and winter of 2019 with anticipation of construction in 2020. 

For information about the other stages of Veterans Trail, take a look at the project story map.

Hunting Hollow Drive

A portion of Veterans Trail connecting Valley View Road and Prospect Street will utilize Hunting Hollow Drive. Three possible alignments along Hunting Hollow Drive were provided to the residents. A form was included for them to select their preferred option and return for use in the City’s analysis. Click here to view the Trail Options Letter mailed on August 9, 2017.

Click image to view a larger map:

Veterans Trail Phase 2 Concept Plan

Hunting Hollow Trail Three Options:

  • Option 1 is a 10-ft wide sidewalk along Hunting Hollow Drive. The path would be located on the south side of the road, within the City’s right-of-way.
  • Option 2 is a 12-ft wide asphalt path. This option would be located in the Ohio Edison easement behind the homes along the turnpike.