2021 Sidewalk Projects

As part of the Sidewalk and Trail Master Plan 2021-2025, five sidewalk projects will take place in 2021. Several others for upcoming years will also be designed this year. Questions about the Sidewalk and Trail Master Plan or how these projects may affect your property? View the Frequently Asked Questions here or at the bottom of this page.

Middleton Road and Stow Road Sidewalk Project (2022)

Project Description

The City is preparing for construction of the upcoming Middleton Road and Stow Road Sidewalk Project located between State Route 91 & High Point Park, which is scheduled for construction in Summer 2022. 

A new 5 foot wide, approximately 2.5 mile long concrete sidewalk will be installed between S.R. 91 and High Point Park and from Middleton Road north to Chamberlin Blvd. The project will also include the installation of new storm sewer, storm inlets, driveway aprons, portions of ditch elimination, and other miscellaneous utility work along the southside of Middleton Road and eastside of Stow Road. 

The new sidewalk will connect to the new 8 foot sidewalk installed on State Route 91 later this fall and tie into High Point Park. The new walk will safely connect residents to the schools, neighborhoods, the parks, and downtown Hudson as part of the Master Plan.

Herrick Park Sidewalk Project (2021)

Project Update 12/2/2021

The Herrick Park sidewalk has been installed.  The contractor will be back in early spring to finish the installation of the new street lights and to touch up any necessary restoration and landscaping.

Project Update 9/13/2021

The Herrick Park Drive sidewalk project is now underway! (See the project description below for full project details). Short delays may occur during work hours, but two way traffic will be maintained. 

Access to the driveways and properties along the south side of Herrick Park Drive will be open and maintained. The contractor will contact all property owners one day in advance for any closures or work within your driveway. NOTE: Not work is anticipated on the north side of Herrick Park Drive and there should be no driveway disruptions.

Project Update 8/16/2021

The Herrick Park Sidewalk Project has been bid and awarded to DL Smith Concrete. The project is anticipated to begin in the coming month, weather permitting. During all phases of construction, the contractor will maintain two-way traffic along Herrick Park Drive. During the course of the project, the City will have a City representative on site monitoring the contractors work.

Project Description

The City is preparing for construction of the upcoming Herrick Park Drive Sidewalk Project located between State Route 91 & Lascala Drive, which is scheduled for construction in Summer 2021. 

A new 5 foot wide, 3,000 foot long concrete sidewalk and curb will be installed between 7456 and 7754 Herrick Park Drive. The project will also include the installation of new storm sewer, storm inlets, driveway aprons, ditch elimination, and other miscellaneous utility work along the southside of Herrick Park Drive. 

The new sidewalk will connect to the new 8 foot sidewalk to be installed on State Route 91 later this fall and also to the existing sidewalk at the Lascala Drive intersection. The new walk will safely connect residents to the schools, the parks, and downtown Hudson as part of the Master Plan.

To sign up to receive project updates via email, visit www.hudson.oh.us/HerrickParkUpdates

Resources

North Darrow Sidewalk Project (2021)

Project Update 12/2/2021

The North Darrow sidewalk has been installed.  The contractor will be back in early spring to finish the installation of the Rectangular Rapid Flashing Beacon (RRFB) and to touch up any necessary restoration and landscaping.

Project Update 9/15/2021

The North Darrow Sidewalk Project is currently out to bid . The project is anticipated to begin in October of 2021, weather permitting. 

Project Description

This project will include the installation of a concrete sidewalk on North Darrow Road (SR 91) from Garden Lane to the Twinsburg Township Line. A new 5-foot wide concrete sidewalk will be constructed on the east side of Darrow Road between Garden Lane and Wren Haven, and on the west side between Christine Drive and the Corporation line which will incorporate a curb and a 6-foot concrete sidewalk. The project will also include the installation of new storm sewer infrastructure, driveway aprons, and miscellaneous utility work.

W. Barlow Sidewalk Project (2021)

Project Update 2/7/2022

As you may have noticed, the concrete sidewalk installation was completed prior to the onset of winter weather.  However, all of the final grass restoration had not been completed.  The contractor will be returning to the site in the spring to complete site cleanup and all grass restoration on the project.

Project Update 9/30/21

The construction of the Barlow Road Sidewalk Improvement Project began on Monday, September 27.

The contractor will be closing Barlow Road to east bound traffic only beginning Monday, October 11th for 30 days. West bound traffic will be maintained (one way traffic only). A signed detour will be in place for east bound traffic to use Terex Road and Darrow Road.

Project Description

This project includes the installation of a sidewalk along the northside of Barlow Road between Nicholson Drive and SR 91.

South Darrow Sidewalk Project (2021)

Project Update 3/24/2022

The Contractor will be on site starting the week of 3-28-2022 to begin laying out the path of the new sidewalk and underground work. Construction will commence the week of April 4th, 2022 and last for approximately 3 months. One lane traffic will be maintained throughout the day going south bound on SR 91 between Corporate Drive and Norton Road.  Two way traffic will be maintained outside of construction hours and on the weekends.  Minimal delays should be expected during 7:00AM and 4:30PM. 

Project Update 2/7/2022

The South Darrow Sidewalk Project has been bid and awarded to CATTS Construction. The project is anticipated to begin in April, weather permitting. During all phases of construction, the contractor will be utilizing the far right south bound lane for a working zone.  The zone will be set up and tore down daily within the hours of 6:45 am and 4:30 pm. Contractor will maintain one-way traffic along SR 91 between Corporate Drive and Norton Road.. During the course of the project, the City will have a City representative on site monitoring the contractors work.

Project Update 12/2/2021

The project design has been finalized and the contract is out to bid.    Construction of the project is anticipated in the spring of 2022, weather permitting, but work could start in winter of 2021/2022 if mild temperatures occur.

Project Description

This project will include the installation of a sidewalk on South Darrow Road (SR 91) just north of Norton Road to Corporate Drive. To sign up to receive project updates via email, visit www.hudson.oh.us/SouthDarrowUpdates.

Resources

W. Streetsboro Sidewalk Project (2021)

This project will include the installation of a sidewalk on W. Streetsboro Street (SR 303) from West Case to Nicholson Drive.


View All FAQs